Targeted structural repairs and composite redecking on an existing two-level elevated deck in Lee’s Summit, retaining serviceable flush beams and joists while replacing all support posts, pouring new concrete piers, reinforcing framing, and installing Deckorators Summit Glacier composite decking and Fortress metal railing.

Project Overview
This Lee’s Summit project focused on targeted structural deck repair and composite redecking rather than a full tear-down or expansion. The two existing elevated deck platforms kept approximately their original footprints, profile, and heights. Once the deteriorated wood decking and railings were removed, the underlying framing was evaluated directly: the existing flush beams and joists were serviceable and retained, blocking and framing reinforcement were added where required, and every support post was replaced with pressure-treated 6x6 posts set on new 16-inch diameter by 36-inch deep concrete piers. Both platforms were then resurfaced with Deckorators Summit composite decking in Glacier with picture-frame borders, matching composite fascia, and Fortress metal railing topped with composite cocktail rail caps. No stair reconstruction or stair work was part of this scope.
Key Selections
- Deckorators Summit composite decking — Glacier
- Picture-frame deck borders
- Matching composite fascia
- Fortress metal railing with composite cocktail rail caps and Fortress cocktail-rail brackets
- Pressure-treated 6x6 replacement support posts
- New concrete piers (16-inch diameter, 36 inches deep)
Before



During Construction




After



What We Had to Solve
Evaluating what to keep versus replace: the original two-level wood deck had heavily weathered decking and railings, but the existing flush beams and joists remained serviceable. Removing the old surface materials allowed the framing to be inspected directly so sound structural members could be retained rather than demolished unnecessarily.
Targeted structural repairs: all existing support posts were replaced with pressure-treated 6x6 posts supported on new 16-inch diameter, 36-inch deep concrete piers. Where the retained joist framing needed additional support for the new surface and railing, blocking and framing reinforcement were added.
Composite redecking and railing installation: both the upper and lower platforms were finished in Deckorators Summit composite decking in Glacier with picture-frame borders and matching composite fascia to reduce ongoing wood-surface upkeep. Fortress metal railing was installed around the platforms with composite cocktail rail caps mounted using Fortress cocktail-rail brackets.
Defined scope boundaries: the two elevated platforms retained approximately their original footprints, profile, and heights. This project was structural repair paired with composite redecking—not a complete deck rebuild, not a deck expansion, and with no stair reconstruction or stair work.
By pairing new 6x6 support posts, new 16-inch by 36-inch concrete piers, and targeted framing reinforcement with the serviceable existing flush beams and joists, the two-level deck gained a lower-maintenance Glacier composite surface and new Fortress cocktail-rail metal railing while keeping its established layout.